Under 29 CFR 1910.119, which is an example of a Management of Change (MOC) trigger that a CIRO-level supervisor must ensure is routed through the MOC process?
Correct Answer:
Changing the refrigerant charge capacity by adding a new low-temperature evaporator circuit