A weaving plant manager calculates that 10 machines operating at full capacity for eight hours will yield 1450 meters of cloth. Owing to various technical issues, 6 machines operate at 90% efficiency while 4 operate at 95% efficiency. In eight hours, how many meters of cloth can be produced by these machines?
Correct Answer:
1334 meters