According to the manager of a weaving mill, ten machines could create 1450 meters of cloth if they operated at 100% efficiency for eight hours. Four machines operate at a 95% efficiency due to technical issues, while the remaining six operate at a 90% efficiency. In an eight-hour period, how many meters of cloth can these machines produce?
Correct Answer:
1334 meters