Your organization has just completed an expensive customer discovery sprint. The data reveals that your top two priority features — which are already 70% built — are not valued by any of your interviewed customer segments. What should a distinguished Product Owner do?
Correct Answer:
Immediately stop work on both features, cancel the remaining work, make the decision transparent, and re-order the Product Backlog based on validated customer value; treat the earlier investment as learning, not loss.