An organization running five Scrum Teams on the same product finds that each team defines 'Done' differently, resulting in integration failures at the end of each Sprint. Teams are resistant to a unified Definition of Done because they feel it will slow them down. How should the Scrum Master approach this?
Correct Answer:
Facilitate a cross-team working session to collaboratively create a shared Definition of Done, making the cost of inconsistency visible and letting teams co-own the result