A Scrum Team has just started a Sprint. During the Daily Scrum, a Developer realizes they cannot complete their selected Sprint Backlog item due to a technical dependency. What should they do?
Correct Answer:
Collaborate with other Developers to adapt the Sprint Backlog and re-plan the work needed to achieve the Sprint Goal