During a Sprint, the Developers realize their initial plan for delivering the selected Product Backlog Items is flawed and will not achieve the Sprint Goal. What is the MOST appropriate course of action?
Correct Answer:
Adapt the Sprint Backlog by creating a new plan to meet the unchanged Sprint Goal.