A project manager is leading a team that is new to Agile. The organization's leadership is also accustomed to traditional, plan-driven project reports and milestones. To ease the transition and ensure stakeholder comfort, the project manager decides to use two-week sprints for development and daily stand-ups, but also maintains a high-level project schedule with key milestones and provides monthly status reports in a traditional format. This is an example of what?
Correct Answer:
Tailoring a hybrid approach