During Managing Product Delivery, a Scrum team completes a sprint but the product owner has not accepted two user stories due to failing acceptance criteria. According to PRINCE2 Agile, what should happen NEXT?
Correct Answer:
The incomplete stories are renegotiated with the product owner, re-prioritised in the backlog, and worked on in the next iteration