During a project's Controlling a Stage process, the team is using Kanban. The project manager notices that the team's WIP limit is being consistently breached. According to PRINCE2 Agile, what is the MOST appropriate immediate action?
Correct Answer:
Investigate with the team to understand the cause and whether flow needs rebalancing