PMI GMetrix Practice Test
Access More Questions
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
What is a work breakdown structure (WBS) and what should it represent?
A hierarchical decomposition of the total scope of work; represents deliverables and sub-deliverables
A chart showing project schedule with milestones
A list of project risks and mitigation plans
A communication plan for stakeholders
Reveal Answer
Correct Answer:
A hierarchical decomposition of the total scope of work; represents deliverables and sub-deliverables
Explanation:
The main idea behind a work breakdown structure is to map the project by turning the total scope into a structured set of deliverables. It represents the final product and all its components broken down into smaller, more manageable pieces. Each level adds detail, ending with work packages that can be clearly estimated, assigned, and tracked. Because it focuses on what will be produced rather than when or how it will be done, a WBS ensures nothing essential is left out and that every deliverable and sub-deliverable is accounted for. So, the WBS should capture all deliverables and their sub-deliverables, forming a hierarchy that defines the scope in terms of outcomes, not activities. This clarity makes planning, budgeting, and assignment straightforward, and it provides a stable basis for further planning like scheduling and resource allocation. A schedule chart, risks list, and a stakeholder communications plan serve different purposes: the schedule shows timing and milestones; the risks list identifies uncertainties and mitigation steps; the communications plan outlines who needs what information and how.