In a critical path method (CPM) schedule, Activity A has a duration of 5 days, Activity B has a duration of 8 days, and Activity C has a duration of 4 days. Activity C can only start after both A and B are complete. What is the early start (ES) for Activity C?
Correct Answer:
8 days