NM CID GF-9 Practice Questions - New Mexico CID GF-9 Utility Lines Contractor Examination Exam

Access More Questions
When filling a new PVC or ductile-iron water main for hydrostatic testing, why is the line filled slowly with air valves open?
Correct Answer:
To expel trapped air that would make the test spongy, dangerous, and misleading

Access more questions from this quiz

Continue to NM CID GF-9 Practice Questions - New Mexico CID GF-9 Utility Lines Contractor Examination Exam for more practice questions and the full quiz experience.

Access More Questions