A deluge system protects a turbine lubricating-oil skid where water discharge would damage the equipment unless the unit is shut down. Per NFPA 25, full-flow trip tests must be coordinated with plant shutdowns, but the interval between full-flow tests must not exceed:
Correct Answer:
3 years