A homeowner contracts with a builder to construct a pool for $40,000. After completing 60% of the work, the builder repudiates and walks off. The homeowner pays another contractor $30,000 to finish. What is the homeowner's expectation measure of damages against the breaching builder?
Correct Answer:
$$30,000 paid to complete, minus the portion of the contract price not yet paid to the original builder (cost of completion measure)