In a process with a takt time of 3 minutes and a pack-out quantity of 35 parts, the Pitch is
Correct Answer:
105 minutes
Explanation:
Pitch is the interval between the starts of successive packs, tying the cadence to both takt time and batch size. With a takt time of 3 minutes per part and a pack-out of 35 parts, the time to complete one pack is 3 minutes × 35 parts = 105 minutes. So the pitch is 105 minutes, meaning a new pack would be started every 105 minutes to maintain the cadence with takt time.