A project has a Budget at Completion (BAC) of $1,200,000. Currently, the Earned Value (EV) is $400,000, and the Actual Cost (AC) is $500,000. If the remaining work is expected to be performed at the budgeted rate, what is the Estimate at Completion (EAC)?
Correct Answer:
$$1,300,000