In a Swiss construction contract based on unit prices (Einheitspreisvertrag), how is the total remuneration owed to the contractor legally calculated upon completion?
Correct Answer:
By multiplying the predetermined unit rates by the quantities of work and material actually and effectively executed as established by joint or verified measurement (Ausmass).