A Lean Six Sigma Black Belt is evaluating four candidate projects for an enterprise deployment pipeline. The leadership team prioritizes Net Present Value (NPV) and risk alignment. Project A has an initial investment of $200,000 and generates cash flows of $80,000 per year for 4 years at a discount rate of 10%. What is the NPV of Project A (rounded to the nearest dollar)? (Discount factors at 10%: Year 1 = 0.9091, Year 2 = 0.8264, Year 3 = 0.7513, Year 4 = 0.6830)
Correct Answer:
$$53,584