A key component vendor encounters supply chain delays, threatening to delay Stage 2 completion by 4 weeks. The Project Manager evaluates scope prioritization and finds that deferring two 'Could-have' features can recover 3 weeks of delay. What should the Project Manager do?
Correct Answer:
Evaluate whether the scope reduction compromises Must-have requirements; if core benefits remain viable within Business Case parameters, present the option to the Project Board for approval.