During Stage 3 execution, external market analysis indicates that customer demand for the primary project outcome has dropped by 30%, reducing anticipated financial benefits. How should the Project Manager handle this scenario under DPMM?
Correct Answer:
Update the Business Case with the revised benefit projections, conduct a stage boundary review, and submit the updated Business Case to the Project Board to re-confirm ongoing business justification.