A DPMM project has an approved cost target tolerance of +5% and a time target tolerance of +2 weeks. Midway through Stage 2, unforeseen regulatory compliance requirements increase projected costs by 12%, while the schedule remains on track. What is the correct action for the Project Manager?
Correct Answer:
Raise an exception to the Project Board, because the cost tolerance (+5%) is breached even though time remains within tolerance.