ENADE Engenharia Elétrica Practice Questions - ENADE Engenharia Elétrica - Exame Nacional De Desempenho Dos Estudantes Exam

Access More Questions
In the context of the Brazilian National Environmental Policy (PNMA - Law 6.938/1981) and CONAMA Resolution 001/1986, which statement correctly evaluates the environmental impact assessment for major power generation projects?
Correct Answer:
Hydroelectric power plants with significant reservoir flooding require an Environmental Impact Study and Report (EIA/RIMA) with public hearings, whereas utility-scale solar and wind projects undergo specific simplified or regular licensing based on local ecosystem sensitivity.

Access more questions from this quiz

Continue to ENADE Engenharia Elétrica Practice Questions - ENADE Engenharia Elétrica - Exame Nacional de Desempenho dos Estudantes Exam for more practice questions and the full quiz experience.

Access More Questions