CMPM Practice Exam
Access More Questions
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
What is a baseline in project management?
A baseline is a risk register.
A baseline is the approved version of project scope, schedule, and cost against which performance is measured.
A baseline is a list of stakeholders.
A baseline is a vendor contract template.
Reveal Answer
Correct Answer:
A baseline is the approved version of project scope, schedule, and cost against which performance is measured.
Explanation:
A baseline in project management is a fixed reference point used to measure project performance. It represents the approved version of the plan, including the project scope, schedule, and cost, against which actual work is compared. Once these elements are approved, they become the standard for tracking progress, detecting variances, and deciding whether changes require formal change control. This allows you to assess whether the project is on track and manage any deviations effectively, sometimes using methods like earned value management. The other options aren’t baselines: a risk register is a log of identified risks and responses, not the performance reference; a stakeholder list is a communications or stakeholder register; a vendor contract template is a document used for procuring goods or services, not a baseline for measuring performance.
Access more questions from this quiz