Certified Risk Architect (CRA)
Access More Questions
Report question problem
×
I think the answer is wrong
There are multiple correct answers
There is a typing error
Image or comprehension text is not display properly
Something else(please specify below)
Any more information
What does Recovery Time Objective (RTO) define in business continuity planning?
The total budget allocated for recovery operations
The maximum acceptable time to restore a business function after a disruption
The minimum number of staff required for recovery operations
The maximum allowable distance to a backup facility
Reveal Answer
Correct Answer:
The maximum acceptable time to restore a business function after a disruption
Access more questions from this quiz
Continue to Certified Risk Architect (CRA) for more practice questions and the full quiz experience.