Which statement describes the purpose of an erosion control plan during construction?
Correct Answer:
It outlines temporary measures to control erosion during construction.
Explanation:
An erosion control plan during construction is all about preventing sediment from leaving a disturbed site while work is in progress. It outlines the temporary measures and practices used to control erosion and manage stormwater during the construction phase, including where to install silt fences, sediment basins, inlet protection, stabilized entrances, temporary seeding or mulching, and how exposed soils will be stabilized as work proceeds. The plan also guides the sequencing of activities and inspections to keep controls functioning as the site changes, and it’s designed to meet regulatory permit requirements. It’s not about permanent landscaping after completion, it isn’t limited to stormwater discharge limits alone, and it isn’t optional in regulated projects.

Access more questions from this quiz

Continue to Certified Inspector of Sediment and Erosion Control (CISEC) Practice Exam for more practice questions and the full quiz experience.

Access More Questions