A foundation drawing requires 12 continuous runs of #5 rebar in a 200-foot footing. Each run has 4 lap splices requiring 30 inches of overlap. Knowing #5 rebar weighs 1.043 lbs/ft, what is the total estimated rebar weight?
Correct Answer:
2,628 lbs of reinforcement