A contractor must estimate ready-mix concrete for 10 line post footings, each 12 inches in diameter and 36 inches deep. Including a 15% waste allowance, what total volume of concrete should be ordered?
Correct Answer:
Approximately 1.00 cubic yard of ready-mix concrete.