A residential building site requires removing 1,500 bank cubic yards (BCY) of dense clay during basement excavation. If the clay has a verified swell factor of 25%, what total loose volume in loose cubic yards (LCY) must be hauled away by dump trucks?
Correct Answer:
1,875 LCY