An earthmoving contractor needs to place 2,000 compacted cubic yards (CCY) of embankment fill. The borrow soil has a shrink factor of 15% relative to bank measure and a swell factor of 20% from bank to loose measure. How many loose cubic yards (LCY) of borrow soil must be hauled?
Correct Answer:
2,824 LCY