Consider a decision tree with two options. Option A: invest $100k now; 70% probability the project succeeds yielding $300k revenue, 30% it fails yielding $0. Option B: do nothing, $0 cost, $0 revenue. The EMV of Option A is:
Correct Answer:
$$110,000