NICET Level 3 Water Based Layout Exam 163 Questions And Answers Set 02

EXAMS AND CERTIFICATIONS 163 Terms | NICET Level 3 Water Based Layout Exam 163 Questions And Answers Set 02
1 / 10
Terms in this set 163
What is not included in the technical specification?
General Conditions
Bid documents include?
•contract
•specifications
•contract drawings
General Conditions
Codes, standards, Authority Having Jurisdiction (AHJ), clean-up, safety requirements, barricades, fencing, insurance and bond requirements, ect.
Supplementary Conditions
Addendums, time schedules, working days allowed, delay agreements, payment schedules
Specifications typically use what format?
Construction Specifications Institute (CSI)
Construction manager concept is when the owner contracts with the construction manager who oversees ____________ working on the project
Contractors
Sometimes referred to as a turn-key type agreement or contract?
Design-Build Concept
Multiple Prime Contractor Method has the intent is eliminate the middleman __________ __________.
general contractor
Multiple prime contractor method involve more than one prime contractor which consist of?
•architectural/structural contractor
•mechanical contractor
•electrical contractor
Who commonly uses the multiple prime contractor method?
•federal government
•general services administration (GSA)
•large companies